Work Area by Alignment always starts at zero The tool always gives the start location station as 0, irrespective of the actual alignment property. Schedule/Work Areas are based on station points, so we have to manually do tons of calculations to select the correct points of slicing.
Work Area Tool Start Location should have option to use project stationing
Merged